Officials said a recent 5-0 decision tied to Justice Kavanaugh’s opinion clears administrative obstacles for a rail project and allows agencies to resume work, but legal challenges and environmental reviews will continue to shape timing and mitigation requirements.

A recent unanimous high‑court opinion and accompanying commentary from Justice Brett Kavanaugh has cleared a major legal obstacle to a regional rail project, county officials said at the Duchesne County meeting. Speaker 2 described the ruling as “what we had hoped would happen,” saying it undercut a prior decision from the D.C. Circuit that had halted work tied to the Surface Transportation Board’s authorization.

The decision, Speaker 2 said, means the Surface Transportation Board can move to reinstate the project and cooperating federal agencies — including the U.S. Forest Service, the U.S. Fish and Wildlife Service and the Bureau of Indian Affairs — will need to resume elements of their review and mitigation planning. Speaker 2 added that the Center for Biological Diversity has vowed to continue legal challenges, but “they’ve got a steeper road to hoe now.”

Why it matters: The ruling clears the way for engineering crews to return to field work that had been paused pending litigation, potentially accelerating construction timelines and permitting activities. Officials said some follow‑up steps remain: sensitive‑species surveys and other agency actions will be required before ground work proceeds broadly.

What leaders said: Speaker 2 framed the outcome as a win for the county and for a seven‑county infrastructure coalition, adding that reviews tied to the National Environmental Policy Act (NEPA) have delayed or increased the cost of projects in the past. “Projects have been held up or gotten way more expensive because of the abuse that’s happened with NEPA,” Speaker 2 said.

Next steps: County leaders said they expect federal agencies and the Surface Transportation Board to complete administrative steps within statutorily guided windows; they also signaled readiness for additional surveys and mitigation work requested by federal wildlife authorities. Legal risk remains while outside groups indicate they will continue to press challenges.