Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Parks Budget topic
No spam. Unsubscribe anytime.
Council approves $406,025 for Legacy Park phase 1, adding electrical conduit and food-truck pedestals
Summary
The Mendon City Council voted to add two bid items to Legacy Park phase 1, increasing the project total to $406,025; the mayor directed staff to schedule a January budget hearing to move existing funds and cover the additions.
Get email alerts on the Parks Budget topic
No spam. Unsubscribe anytime.
Mendon — The City Council voted to add two bid items to Legacy Park phase 1, raising the phase total to $406,025.
Councilmember Amy moved that the council add the electrical conduit and food-truck pedestals from the Staker Parsons bid to the project. "I motion that we add the 2 additional items as bid by Staker Parsons to the Legacy Park phase 1, bringing the total for the Legacy Park phase 1 to 406,025," Amy said during the meeting. A second was made and the council approved the motion by voice vote.
Why it matters: The additions cover site electrical infrastructure and pedestals intended to support food trucks and events, items council members said are important to realizing the park’s intended uses. City staff said existing grants and fundraising should cover most of the new costs, but the mayor directed staff to schedule a January budget hearing to reallocate line items and formalize the adjustments.
Details: At last month’s meeting the council accepted the base bid for the project; council discussion at this meeting clarified that the earlier base bid was roughly $372,780 and that adding the two listed items would bring the phase 1 contract to $406,025. The mayor asked staff (Marilyn and Jim) to set a budget hearing in January to move funds as needed.
Next steps: The council approved the change by voice vote and staff will bring formal budget adjustments to the January budget hearing for public comment and final action.