Water board hears project updates: irrigation expansion, culinary tanks, new wells and Dixie Springs
Summary
After the impact‑fee discussion, staff updated the board on the irrigation expansion (completion slid from Jan. 1 to June 1), culinary water tank and pipeline repairs, new‑well drilling progress and a deferred Dixie Springs infrastructure and rate discussion.
Get email alerts on the Infrastructure Updates topic
No spam. Unsubscribe anytime.
Following its vote on the impact‑fee plan, the board received several operational updates.
Irrigation expansion: Staff said concrete work and pond inlet/outlet construction are under way but the project completion slipped from Jan. 1 to June 1 because of weather and parts delays; crews expect to resume pours and continue pipeline tie‑ins.
Culinary tanks and pipeline: Staff reported the pipeline trenches are dug at joints and crews have encountered leaks caused by deformed ductile iron pipe; repairs (cutting in dressers and replacing short sections) continue and tank pours will proceed once preparation is complete.
Wells: The Goulds Wash pilot hole and camera inspection found caverns and murky material down to ~300 feet; chemical treatment is planned to settle the mud before drilling to the target 800 feet. Sky Ranch well mobilization is in progress and staff is expediting start‑card paperwork with a mayor‑signed letter.
Dixie Springs and water rates: Staff said Dixie Springs infrastructure difficulties remain and the board will resume a detailed water‑rate discussion in January after additional data review.
Board members asked for funding updates and for staff to notify council if project timelines or funding needs change.