City updates Sky Ranch tank, well work and Dixie/Sand Hollow well; Dixie Springs temporary start awaiting state approval

Hurricane City Council · January 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works reported progress on a 2,000,000‑gallon Sky Ranch tank (foundation forming), Sky Ranch well drilling, a completed tested main water line, irrigation expansion across 650 South, and a near‑ready Dixie Springs well pending state temporary startup approval.

City water department staff provided progress updates on several capital projects and near‑term operational steps.

The department reported that the 2,000,000‑gallon tank near Sky Ranch has foundation forms in place and is preparing for concrete pours. Crews have installed and successfully tested the main water line feeding that tank and the Sky Ranch well drilling is underway. An irrigation expansion project is progressing on 1100 West and will continue up 650 South; crews also reported pond floor pours on the south side with wall work to follow.

Officials said the Dixie Springs (Sand Hollow) well is close to a temporary startup but remains subject to final state approval. "We are ready to go... we're just waiting on the state to give us that final permission to start them up," a city water official said during the meeting.

The department is hiring to fill open positions and expects a staff retirement on Feb. 13. No specific construction costs or funding totals were disclosed in the open briefing.

Next steps: staff will continue construction progress, complete required construction tasks and coordinate with the state for Dixie Springs' temporary startup approval.