Council asks region to return with comprehensive plan for Jenkins Flat Reservoir dredging

Wildlife Habitat Council · March 22, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Faced with a near-$376,000 dredging estimate and concerns that upstream sediment sources were not addressed, the council asked Central Region staff and the Forest Service to return with a broader watershed restoration plan before committing funds to Jenkins Flat Reservoir dredging.

Central Region sport-fish biologist Tyler Robinson presented an urgent request to restore Jenkins Flat Reservoir, which has accumulated an estimated 18,000 cubic yards of sediment since major post-fire runoff. Early cost estimates from five years ago have risen because the Forest Service’s regulations (visual-byway constraints) prevent leaving sediment on-site; that pushed a prior $80,000 estimate to about $376,000 because sediment must be hauled 10–15 miles to a gravel pit.

Council members raised a series of objections: several argued that dredging without upstream stream-stabilization would only postpone recurrence, others asked why the Forest Service had not managed sediment on its own lands, and still others suggested partnering to find nearer disposal or re-use options (roadbase) to lower costs. One member characterized dredging alone as incomplete without a watershed-level sediment management plan.

After extended discussion, Drew moved and Angie seconded a motion asking the region and partners to return with a more comprehensive approach—explicitly addressing upstream sediment sources and clarifying Forest Service commitments—rather than funding the current dredging scope. The motion passed by voice vote.

Next steps: the region will work with the Forest Service and Juab County road crews to evaluate nearby disposal options, draft a watershed-scale sediment/stabilization plan, and return with a revised proposal that integrates upstream restoration and clearer partner roles.