Citizen Portal

Staff recommends awarding Hub Rest Area/T‑Mobile Plaza contract amid grant support and budget gap

North Bend City Council · January 27, 2026

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff recommended awarding the Hub Rest Area/T‑Mobile Plaza construction contract to Knight River after seven bidders responded; staff said the low bids were below seasonal expectations but roughly $200,000 over the initial estimate and that grants (including a $142,000 landscaping grant and $200,000 from T‑Mobile/Bridal Oregon) and additional funding or value engineering will be used to close the shortfall.

City project staff and the contracted architect briefed the council on the Hub Rest Area and T‑Mobile Plaza project, reporting strong bid turnout and recommending award of the construction contract to Knight River.

Staff said the project received multiple funding sources, including a $200,000 contribution associated with T‑Mobile and an additional landscaping grant of approximately $142,000 that the planner said covers about 45% of the landscaping included in this phase. The architect and staff reported seven bidders — more than recent averages — and said the low responsive bid nevertheless ran roughly $200,000 above the city’s original budget estimate for construction; staff said bid timing and subcontractor bid spreads partly explained the variance.

“Architect and staff are recommending we award this to Knight River,” a staff speaker told the council, while also noting staff have identified potential value‑engineering options and will seek other grant opportunities to cover remaining costs. Project leaders said a contract should be ready for council signature by mid‑March and construction will be phased (including placing a pad for an on‑site boxcar relocation and subsequent landscaping). Staff also said Energy Trust analysis improves the prospects for a solar carport grant to cover long‑term power needs.

Councilors and staff discussed schedule and grant timing; staff said funds are expected to be available to reimburse or apply in March and that some landscaping could be done later as a separate project if needed. Staff recommended proceeding with the award to avoid further price escalation, while noting additional funds or changes may be required to complete all elements in the master plan.