RCTC approves cooperative agreement with SCRRA for Mead Valley Metrolink Station

Riverside County Transportation Commission (RCTC) WRC Committee · November 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

RCTC approved a cooperative agreement with SCRRA for project support services at the Mead Valley Metrolink Station mobility hub and recommended a project design and contingency budget that leverages $40.5 million in TIRCP funds to contribute to a total project estimate of about $50.5 million.

Joy Edelis Yanez presented the Mead Valley Metrolink Station Mobility Hub project, a new station in the unincorporated Mead Valley community near I-215 and Cajalco Road/Ramona Expressway. RCTC secured $40,500,000 in Transit and Intercity Rail Capital Program (TIRCP) funds and, combined with State Transit Assistance and Measure A funds, staff said the project is fully funded for environmental, design and construction phases to a project total of about $50,500,000.

Planned features include two passenger platforms to allow simultaneous boarding, an at‑grade pedestrian crossing with active warning devices, canopies, bike lockers, a bus loop with two loading bays, kiss-and-ride lanes, and a parking lot designed for up to 1,000 spaces constructed in phases (half initially). RCTC will enter a cooperative agreement with the Southern California Regional Rail Authority (SCRRA) for project support services; staff recommended approval of a cooperative agreement not-to-exceed $750,000 for SCRRA review and project support. Staff also recommended a larger contingency (~30%) for design agreements given recent cost escalations on similar SCRRA projects.

A motion to approve the recommended action was made and seconded; roll-call vote recorded affirmative votes and the item passed.

Next steps: initiate environmental and design this fall pending agreement execution; target environmental and design completion by 2028 and construction start thereafter with anticipated opening in 2030.