Airport board approves tinted glazing for tower after vendor withdrawal

Cache County Airport Authority Board · April 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Cache County Airport Authority board approved a motion to install tinted plexiglass on the airport tower after the original glass contractor backed out; tinted glazing will remain under the approved grant cap and was approved by voice vote.

The Cache County Airport Authority board voted to proceed with tinted plexiglass on the airport’s new tower after the contractor’s originally proposed glass supplier withdrew.

Bob, an airport staff member reporting to the board, said Bennett’s Glass declined to supply the glazing because of how the angled panels would be installed. Gordon’s Glass offered to install untinted plexiglass for about $31,000 or tinted for about $39,000; both prices remain below the $48,000 grant that the project can draw on. Board members discussed alternative cosmetic film and durability concerns before taking a vote.

Why it matters: the tower glazing is a visible, capital item funded in part by a grant. The board said it wanted a durable, low-maintenance solution that also fits the previously approved budget. Approving tinted plexiglass avoids a delay while staff obtains additional vendor quotes and keeps the project within the grant ceiling.

Details: board discussion focused on whether to accept untinted plexiglass with aftermarket film or pay more for factory-tinted glazing. One board member asked for clarification on prior approvals; staff said the original accepted bid was checked and confirmed. A motion to proceed with tinted glass was seconded and carried by voice vote; no roll‑call tally was recorded in the meeting minutes.

Next steps: staff will obtain required additional quotes and proceed with procurement steps consistent with the board’s direction and the grant terms. Any contract award or amendment will be returned to the board if required by procurement rules.