After long debate, Visalia council directs staff to study funding for 50-meter pool and large recreation pool

Visalia City Council · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Following a consultant presentation estimating $25'$33 million to build a 50-meter competitive pool paired with a large recreation pool, the council directed staff to return with funding options (including phased approaches) and to hire a consultant to test the viability of a November sales-tax measure; the motion passed 3-2.

The Visalia City Council directed staff to pursue further feasibility and funding analysis for a municipal aquatics complex that would include a 50-meter competitive pool and a large recreation pool, after hearing detailed cost and program options from an industry consultant.

Dennis Berkshire of Aquatic Design Group outlined three facility options based on a 50-meter competitive pool combined with increasing amounts of recreation water. Berkshire said a full build with a substantial recreation component would likely require a 3'5-acre site (plus parking and support) and estimated construction costs in the range of $25 million to $33 million depending on recreation scope, site and shared parking opportunities. He also explained operating assumptions: recreation admissions, lessons and programs typically account for the largest shares of revenue while salaries and utilities are the primary expense drivers; projected annual operating subsidies were roughly $300,000 to $1,000,000 depending on the option and pricing assumptions.

Council members discussed phasing, funding sources (including sales-tax measures, sale of excess land, park impact fees, grants and private naming-rights partnerships) and site preferences. Several councilmembers favored city-owned sites such as East Side Regional Park or a 7-acre parcel near Mooney Boulevard for their size and potential shared parking; others emphasized the need to avoid saddling the city with a large operating subsidy without identified funding.

Public commenters representing swim, water polo and community groups urged the council to act, pointing to long waitlists and the absence of nearby 50-meter pools for hosting meets. One resident asked about corporate partnerships and night lighting, and another suggested solar canopies over parking to offset electricity costs.

In a split vote, the council approved a motion (3'2) to direct staff to return with detailed funding options for total and phased approaches, to assess named sites further, and to retain a consultant to explore the viability of placing a sales-tax measure on the November ballot. The motion passed 3-2. Staff said no city funding was currently allocated and emphasized that advancing the project will require explicit council direction and prioritization of capital resources.

Next steps: staff will develop funding scenarios (including bond/sales-tax options, grants and partnerships), complete site feasibility work and return with project timelines and a recommended path for phasing.