City engineers and staff won commission approval to advertise and award multiple capital projects: street milling and overlay ($1.29M), a Memorial Park baseball building (design-build budget $1.2M, city $1.0M budgeted), roll-off boxes ($77,470) and a semi tractor ($163,324, $3,324 from reserves).
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The commission approved several capital actions, including bidding a major street milling and overlay project, solicitation for a Memorial Park baseball building design-build contract, and awards and purchases for solid-waste equipment.
City engineer Brett Runge told commissioners the annual street milling and overlay (Project 202603) will mostly cover streets north of Highway 14, include work on Long Ridge Avenue and add 9th Street to the project; the total project budget is $1,292,800. Commissioners authorized staff to proceed with bidding with a bid opening set for Feb. 17, 2026.
Runge also described a design-build procurement (Project 2026-05) for the Memorial Park Baseball Building, which includes a player development center, new restrooms and a concession stand. The total design-build construction budget is $1.2 million; the city has budgeted about $1.0 million, with the remaining funds expected from donations, grants and the local baseball association. Commissioners authorized the competitive sealed proposal process with proposals due Feb. 10, 2026.
On equipment, the commission approved awarding bid 2026-11 to Sanitation Products Inc. for five 20-yard and five 30-yard roll-off boxes for $77,470 (budgeted). The commission also approved awarding bid 2026-12 for a new semi tractor to I State Truck Center for $163,324; because the city budgeted $160,000, the additional $3,324 will come from reserves. Solid-waste staff explained fleet needs tied to daily runs to the pier.
All items were approved by roll-call votes during the meeting. Staff said work and procurement steps will follow state bid law and the city's procurement processes.