Council to seek engineering-on-call and installs delineators on Henry Clay Street
Summary
Council agreed to advertise for an on-call streets-and-grounds engineering firm and approved installing flexible traffic delineators as a short-term measure on the subsiding Henry Clay Street while larger engineering scope is reassessed.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Harpers Ferry councilors on Jan. 27 approved steps to secure an engineering-on-call arrangement for streets and grounds and authorized short-term safety measures for a failing section of Henry Clay Street.
Speaker 2 outlined a proposed selection process modeled on past procurements: advertise, select three firms for interviews, then negotiate rates with the top candidate. The on-call engineer would provide surveying and rapid-response guidance for sidewalks, roads and other small public-works problems.
Council reviewed field observations at Henry Clay Street. Speaker 5 recommended a staged approach—seek local pavers for targeted repairs and use flexible traffic delineators to keep vehicles off unstable sections rather than immediate full-scale reconstruction. Speaker 5 moved to install flexible traffic delineators on the damaged segments; the motion was seconded and the chair announced the motion carried (recorded as 6-0).
Council directed staff to place the engineering-on-call advertisement and to have Budget & Finance vet procurement and costs before returning to council.
What happens next: staff will post the advertisement for firms, return cost estimates to Budget & Finance, and schedule follow-up inspections and measurements for the Henry Clay mitigation work.