Council authorized AEW to prepare engineering drawings and bid documents for abandoning the Linden stormwater pump station and rerouting flows after consultants told the council the station sits over historic, irregular sewer routing beneath homes; AEW estimated construction costs could be around $500,000.
Get email alerts on the Infrastructure Stormwater topic
No spam. Unsubscribe anytime.
AEW presented a proposal Dec. 11 for engineering work to abandon the Linden stormwater pump station and reroute storm-sewer flows to active sewers. The consultant said investigation found historic plats and irregular sewer routing that had resulted in storm lines beneath residential structures; AEW reported 10 verified structures built over the sewer and a likely eleventh. The firm recommended preparing construction-ready engineering drawings and bidding documents for $39,000 to enable competitive bids for the construction phase.
AEW noted the 2025 budget estimate for construction had been roughly $300,000 but their more recent planning-level estimate had risen and could be nearer $500,000. Council asked clarifying questions about possible sanitary connections to the storm line; AEW said they are continuing to investigate and would incorporate any required revisions into project plans.
The council moved and approved the AEW engineering proposal (motion carried by voice vote). Staff said the engineering package will help the city refine construction estimates ahead of the next budget cycle. AEW said abandoning the station would remove ongoing operations and maintenance liabilities associated with the asset and reduce risk to homes if the line begins to fail.