Madison County hears update on Yonder Road design, right-of-way and utility coordination
Summary
Wagon Engineering told the Madison County board the Yonder Road project is about 45% complete in work progress, has billed roughly 23–24% of its contract, will affect 73 parcels and faces a delay in environmental review pending U.S. Army Corps of Engineers comments; staff outlined next steps for utility and right-of-way work.
Darren Warren, with Wagon Engineering, told the Madison County board that design and right-of-way work on the Yonder Road improvements (Smith Carr to North Oak Kent Road) is underway and that the firm has billed "about 23 or 24%" of its contract while reporting "around 45%" actual project progress.
Wagon Engineering was hired after the board approved the contract in November 2024 and a December amendment to begin right-of-way acquisition coordination, Warren said. He listed completed work including a right-of-way analysis and parcel impact study,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat