Leon Valley to seek consent placement for El Verdi Road water and drainage upgrade funded by county ARPA grant
Summary
Council heard a first reading for an El Verdi Road project that would replace about 1,200 feet of aging asbestos-concrete main with 8-inch PVC, add services and drainage work; project is fully grant-funded and staff recommended awarding the contract to D and D Construction, with a budget adjustment and reimbursement from Bexar County ARPA funds.
At first reading, assistant public works staff presented plans and budget requests for the El Verdi Road water-main and drainage project.
Staff said the City requested a budget adjustment of $910,893.55 from the enterprise fund reserve to cover engineering, construction and contingency for a project that will replace roughly 1,200 feet of existing asbestos-concrete (AC) pipe with 8-inch PVC, add eight new services and a new fire hydrant,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat