Council hears Old Town Hall update: $3.9 million phase‑2 budget, HUD grant, bids due July 2
Summary
Staff presented an update on the Old Town Hall rehabilitation project, including a $2.1 million HUD community project funding grant, $1.8 million in city general funds (total $3.9M for Phase 2), bids due July 2, and a target occupancy date in mid‑2026. Council discussed paint color, accessibility work, and prior phase expenditures.
City project staff presented a detailed work session update on the Old Town Hall rehabilitation during the June 24 work session.
Andrew Wilson (construction manager) and Saeed Masur (Public Works project manager) outlined the scope of Phase 2: historic exterior and interior repairs, mechanical/electrical/plumbing upgrades, enclosure of rear porches for storage and a new exterior‑access restroom, relocation and replacement of rooftop HVAC units to reduce visibility, and accessibility improvements (front ramp and grade‑level access). Wilson noted the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat