Backup generator projects in Woodstock and Lamoille delayed by exhaust/HVAC design issues; no extra appropriation requested
Summary
Committee heard that backup generator installations in Woodstock ($100,000) and Lamoille (about $190,000) are delayed by exhaust and HVAC design conflicts; BGS said redesign work has not increased the authorized budgets and will proceed when conditions allow.
Committee members reviewed two county courthouse backup generator projects that were appropriated in a prior capital bill but have encountered design snags.
For Woodstock, Speaker 5 said vendor‑recommended exhaust placement risked infiltration into the courthouse HVAC system; the team redesigned the plan to place the generator at the side of the building between…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat