Council accepts community garden and ballfield projects, approves small contract increase
Summary
Council accepted the Sherry Street community garden and Buckingham/Westminster Parks baseball infill projects and authorized a $14,317.28 contract increase to address construction changes; both notices of completion were approved and staff will file county recorder notices.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Council approved acceptance of two capital projects and a modest contract increase tonight.
Sherry Street Community Garden (project PDash2616): staff described a layout of 23 plots (seventeen 4×8 plots at $100/year; six 4×4 at $50/year) and explained design adjustments required concrete footings for five rotated plots; council authorized a contract increase with ZECO Inc. for $14,317.28 to cover the additional work and authorized filing a notice of completion.
Buckingham and Westminster Parks baseball infill renovation (project PDash2613): staff explained that bleachers were added after community input; council discussed design and inspection issues, accepted the project and authorized staff to file a notice of completion with the Orange County Clerk‑Recorder.
Council directed that future notice‑of‑completion reports include before/after photos and additional documentation so council and the public can better see project outcomes.