Council approves Tropicana Field repair contracts and a termination of prior redevelopment agreements

City of St. Petersburg City Council · July 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved insurance/indemnity updates and a $5.26M GMP for stadium lighting and catwalk electrical repairs, accepted license agreements for stadium parcels and voted to terminate earlier gas‑plant redevelopment/vesting agreements; staff said MLB and the Rays are engaged and an October after‑action report to FEMA is planned.

The City Council voted to authorize key pieces of the Tropicana Field repair program and to formalize a termination of earlier redevelopment agreements tied to the stadium.

City real‑estate director Aaron Fish summarized two license agreements for four parcels carved out of the Rays’ current‑use agreement: Parcels 1–3 (about 14 acres) and Parcel 4 (about 2.29 acres). Under the negotiated terms the Rays will pay $400,000 annually for Parcels 1–3 and $12 annually for Parcel 4; the city retained a right to terminate Parcel 4 earlier if the site is needed for redevelopment. Fish also presented a termination agreement to conclude previously negotiated gas‑plant redevelopment and vesting agreements; legal staff confirmed the termination would be effective on the execution date.

Separately, city engineering presented GMP #2 with AECOM Hunt for approximately $5.26 million to replace roughly 100 sport‑lighting fixtures and repair catwalk electrical systems damaged during storms. Staff described a schedule of roof membrane deliveries and a phased installation sequence using safety netting and specialized rigging; the roof membrane (PTFE) bundles were scheduled for staged delivery from August through November.

Council discussion ranged from the legal mechanics of termination to outreach and minority‑contractor participation on upcoming GMPs. Several council members expressed frustration that settlement had not been achieved earlier; others emphasized the city’s contractual obligation to repair the stadium and the legal and financial risks of not performing. Legal staff confirmed that a change of team ownership would not relieve the franchise of the stadium‑use obligations.

Why it matters: The actions marshal city resources and contractual commitments to complete repairs needed for Major League Baseball use through the 2028 season and to protect city assets. Administration noted FEMA, insurance and other reimbursements are being pursued but not guaranteed; staff said they are working to position the city for maximal reimbursement.

Next steps: Staff will continue procurement and shop‑drawing approvals for multiple GMPs (roof, non‑roof items, AV/video, and field work), and provide a forthcoming GMP (GMP #3) addressing interior finishes and mechanical/electrical work. Administration reported outreach work to small and minority businesses led by the Hennessy team; council asked to be notified of subcontracting opportunities so members can connect local firms.

Ending: The council unanimously approved the insurance update to the design‑build agreement and the GMP approval; termination and license agreements were executed contingent on mutual signature, according to staff.