City engineer: DAP-16 vertical work underway; TwinSpan bridge girders to proceed after pump relocation
Summary
City Engineer Patricia Longoria told the board DAP-16 is moving vertical and on schedule (61% of allotted time, 37% of contract amount), irrigation pumps will be moved in February to allow TwinSpan girders installation, and the commercial vehicle parking lot is being poured in sections.
Patricia Longoria, the authority's city engineer, provided a project-status update on capital work including the DAP-16 project, the TwinSpan Bridge and the commercial vehicle parking lot.
"We're already DAP 16 project, we're already starting to move vertical on our coal storage, and they're already starting to pour our…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat