Construction committee: Field house due Feb. 17; classrooms and cafeterias to follow
Summary
Construction committee chair reported a Feb. 17 substantial-completion target for the Metuchen High School Field House with a Feb. 18 move of board offices and mid-March targets for cafeteria and Moss School completion; committee also discussed change orders, punch-list items and exploring ESIP/solar to offset capital costs.
Mr. Glassberg, chair of the construction committee, briefed the Metuchen Board of Education on Jan. 27 about project timelines and remaining work at several district sites.
"February 17 is the expected completion at the Metuchen High School Field House," Glassberg said, adding that a temporary certificate of occupancy is anticipated at that time and that board offices would…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat