Board approves $5.1 million supplemental appropriation for Christiansburg High School to cover change orders and technology needs
Summary
After questioning from multiple supervisors, the board approved a $5,095,650 supplemental appropriation to address change orders and technology shortfalls at Christiansburg High School; school finance staff said change orders totaled roughly $1.35 million and the technology needs had been reduced from original allocations.
The Montgomery County Board of Supervisors approved a $5,095,650 supplemental appropriation on Jan. 28 to address remaining costs on the Christiansburg High School construction and renovation project, tapping bond interest proceeds and other designated funds.
Angela Bland, director of finance for the schools, said the project encountered unforeseen site conditions and change orders totaling approximately $1,350,000 to date, and that the original…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat