Kanosh and Corn Creek Irrigation continue talks over dam SOP and who pays for maintenance

Kanosh Town Council · March 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council reviewed a working draft SOP for Corn Creek Dam and debated whether the 1985 agreement’s section 2.4–2.5 limits irrigation‑company responsibility to irrigation functions; town staff and the irrigation company will meet to define a dividing line and bring attorneys back into negotiations.

Town staff and irrigation company representatives spent the bulk of the meeting walking council members through a working revision of a Standard Operating Procedure (SOP) for Corn Creek Dam that the council said must reflect both dam safety and long‑standing contract language. Stan and other presenters contrasted the town’s revision with language in the 1985 agreement (sections 2.4 and 2.5), noting the irrigation company’s position that they should bear the cost of operation and maintenance for irrigation purposes while the town argued that some maintenance and flood‑control responsibilities fall to the town.

Stan asked for a smaller working group (one town and one irrigation representative) to negotiate specific language and for the council to treat the circulated document as a draft. Neil agreed to be the town’s point person for follow up; council members discussed adding a named emergency contact/dam tender and an Emergency Action Plan (EAP) distribution list. The town attorney reviewed the agreement and suggested simplifying language to a clear yes/no counteroffer where appropriate.

Why it matters: The SOP defines who inspects and maintains the dam, who directs emergency releases and who bears financial and legal liability for failures or corrective work. The council emphasized the public‑safety implications and the need for clarity before approving any final agreement or sharing costs.

Details: The draft assigns inspection, EAP preparation and local coordination duties to the town and operational and repair responsibilities to Corn Creek Irrigation Company except where the work is expressly tied to irrigation. Council members debated measurement criteria (volume, seasonality) to determine what qualifies as "irrigation purposes." The town proposed audit rights so the town could verify claimed irrigation work before contributing money.

Next steps: Town and irrigation representatives will meet to define dividing points (for example, seasonal triggers, flood control vs. irrigation operations), the town will circulate Neil’s draft as a labeled working copy, and both town and irrigation attorneys will continue iterative edits before presenting a final SOP for formal approval.