Council hears update on pump house, valve change order and emergency water-line repair

Lynndyl Town Council · May 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council was told the new pump house is near completion, a valve change order is expected (estimated $5,000–$6,000), pipe costs were about $2,000 higher than expected, and a recent emergency line break that lost ~400 gallons per minute has been repaired by town crews.

Lynndyl — The water department reported construction progress on a new pump house, an expected change order to add an isolation valve, and the resolution of a recent emergency line break.

Speaker 2 said crews had mounted the pump-house doors, completed exterior grouting and started plumbing connections, and that the well plumbing had been tied in. A pending change order will add a valve so the town can isolate the new pump without shutting other wells; Speaker 2 estimated the valve could cost "5 or 6,000" dollars.

Speaker 3 noted pipe costs for the project came back about $2,000 higher than originally estimated but said the overall project remained under budget. Speaker 3 described a recent weekend emergency in which a valve failed, "we were losing 400 gallons a minute," and detailed in-house repairs: staff excavated the break, fabricated a temporary plate and gasket, and restored service by replacing the damaged section of the 8-inch line.

Speaker 2 said the contractor will attach the change order to the first pay request; councilors urged prompt documentation to ensure the project remains on schedule. The town also discussed constructing a concrete pad around a valve box and the logistics of manually mixing and placing donated concrete bags and rebar.

What happens next: Staff will process the pay request and change order documentation, install the valve per plumber recommendation, and continue follow-up on water-line mapping and management.