Council moves to pursue CIB funding for Tar Canyon well; signals preference for utility power
Summary
At a public hearing the council reviewed funding scenarios for the Tar Canyon Well Project, learned of a roughly $6.7 million shortfall, and directed staff to pursue a CIB application while retaining USDA paperwork as a fallback; members expressed consensus to prioritize Rocky Mountain Power service with backup generation included in cost estimates.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Gunnison City Council opened and closed a public hearing Sept. 16 to consider applying to the Community Impact Board (CIB) for partial funding of the Tar Canyon (Tar Canyon/Tarkandi) Well Project and discussed funding scenarios and power options for the proposed well.
Kelly (city staff) told the council the city has already invested about $2.4 million in the project (test well, environmental assessment, water rights, property purchase) and that roughly $6.7 million remains to complete remaining phases, including production well development, a 16-inch transmission line, river crossings, road restoration and a well house. Kelly presented multiple financing scenarios showing the effect of different CIB and USDA Rural Development grant/loan mixes on residential bills; a worst-case 100% loan scenario would raise the average bill by about $35 from an average of $57, while favorable CIB terms could reduce that increase to the teens or single digits.
Councilors questioned an updated MAGI (median annual gross income) figure presented as about $61,000 and discussed commissioning an independent income survey to improve grant eligibility. Kelly said CIB typically expects applicants to have explored other funding and recommended also preparing the PER/EA documentation for a USDA application as a contingency.
On power, staff reported Rocky Mountain Power's concept estimate near $1,000,000 to extend utility service to the well; Kelly also modeled on-site generation plus solar/battery and redundancy with higher upfront cost (about $2.2 million) and greater operations and maintenance needs. After discussion about long-term costs, operational risk and future growth, council members signaled consensus to pursue utility power through Rocky Mountain Power while requiring a backup power source be included in project estimates.
Council voted to close the public hearing after directing staff to submit a CIB application, continue USDA paperwork so the city could move quickly if CIB does not fund the full request, and seek updated power-cost estimates (including the cost of required backup generation). No final funding award or loan/grant terms were approved at the meeting.