County authority approves deductive clinic change order after donated flooring and scope revisions
Summary
The Daggett County Municipal Building Authority approved a deductive change order of $6,823.90 for the new health and community clinic after a local partner donated flooring and contractors adjusted cabinet, specimen pass-through and security conduit scopes.
Get email alerts on the Clinic Project topic
No spam. Unsubscribe anytime.
The Daggett County Municipal Building Authority approved a deductive change order for the county clinic project on Dec. 16 after staff said a partner’s donation and scope clarifications reduced contractor work.
Unidentified Speaker 5 explained that change order number 5 (part of PCO #3) reflects a donated exercise room flooring and equipment funded by a Northeastern grant; because the county will install that donated flooring, the contractor’s flooring line became a credit. Additional adjustments include conduit installed by the electrical contractor for future security cameras, changes to cabinetry in the nurses’ station (Maple Leaf cabinetry), and a specimen pass-through requested by the medical provider.
Unidentified Speaker 5 summarized the net effect as a reduction totaling $6,823.90. Board members reviewed the line items, asked follow-up questions about exact contractor line items and agreed staff should confirm final numbers via email before signatures. Unidentified Speaker 3 moved to approve change order number 5; Unidentified Speaker 1 seconded. The vote carried.
Unidentified Speaker 5 was asked to sign the change order on behalf of the county. Staff said remaining design and installation details (including conduit and cabinet selections) will be coordinated with the provider and contractors, and that a site meeting for the clinic is scheduled for Thursday at 10 a.m.