Transwest delay pushes local work to winter; town expects funds for road upgrades
Summary
Council was told Transwest’s transmission project will not reach the area until late December or January; when work occurs the project is expected to bring funds (bids for Lindletown road updates estimated at ~$163,000), and staff will plan road projects around funding timing.
Get email alerts on the Infrastructure Funding topic
No spam. Unsubscribe anytime.
Chair (Speaker 1) updated the council on Transwest — the transmission-line project that passes behind Lynndyl. A Transwest representative (Joe Tibbetts was the scheduled contact) notified the town that the local portion of the project will be delayed until late December or January because the larger IPP project timeline was extended. The town expects to receive funding tied to the project then and was advised that a Transwest representative will attend the November council meeting.
Council members recalled prior negotiations with the county commissioner (Dean Draper) that led to an offer of either road upgrades after construction or a bid estimate to update affected roads. The council said three bids for updating Lindletown roads totaled about $163,000; members agreed not to schedule work until funds are confirmed and to hold planning for multiple roads until account breakdowns are available.
Staff confirmed Alexis was added to the PTIF account to manage capital funds; councilors discussed fiscal-year timing and noted that when funds arrive the town has ~3 months estimated to complete the road work before the contractor schedule changes.