Davis County officials update plans for Bountiful Branch Library, board recommends remodel over new construction
Summary
Design team and the Davis County Library Board recommended remodeling the existing 1968 Bountiful Branch Library rather than building a new facility, citing program space advantages in the existing footprint, updated cost and geotechnical findings, and a plan to bring a contractor on board for current-market cost estimates.
Get email alerts on the Bountiful Library Design topic
No spam. Unsubscribe anytime.
County officials and the architecture team presented a design update on July 22, 2025, in a Davis County Commission work session, explaining why the Bountiful Branch Library recommendation has shifted from building at a new site to remodeling the existing 1968 building. The county said it has roughly $6 million in construction funding from a prior bond that would be applied to the project.
The key point, presented by the architect Trent Smith, was that the existing building’s larger footprint and internal space make a remodel financially and programmatically preferable in current market conditions. “This is a voluntary seismic upgrade,” Smith said when outlining retrofit options for the structure and clarifying that the remodel would not force full new-construction code requirements unless triggers—such as a change of use or modification above the structural threshold—applied.
Why it matters: county staff and the library board concluded that, with careful design and retrofitting, the existing building can offer more usable space (the team’s programming work estimated needs around 17,500–18,000 sf) than a smaller new building the money would otherwise buy. The team reviewed 2021 feasibility estimates (renovation ~$9 million; replacement ~$10 million on a 24,000 sf basis) and presented updated concept designs showing how a remodel could meet service goals while addressing structural, plumbing and asbestos issues.
What the designers found: geotechnical work showed soft, imported and remediated fill in parts of the site and that new construction would require over-excavation and imported fill to get to target compaction rates. The team also said the building is “lightly reinforced masonry” and that retrofit work would focus on stiffening roof diaphragms and other measures to reach current safety standards without necessarily being designed as a functional-recovery shelter.
Service continuity and schedule: staff acknowledged construction will disrupt services and outlined plans for temporary locations (storefront-style spaces of roughly 5,000–8,000 sf, with an estimated interim cost near $500,000 over the temporary period) to maintain collections and programming. The target for beginning major remodel work was described as near Jan. 1, with a projected roughly 12-month construction window and the possibility of one to two years of interim services depending on findings and remediation (for example asbestos removal).
Next steps: the county plans to issue an RFP and use a construction manager/general contractor (CM/GC) process to bring a contractor on board for aggressive, market-based cost estimating and to refine the selected scheme for budget compliance. Staff also committed to public engagement through upcoming library-board and public meetings.
The commission’s discussion stressed transparency about what a remodel would and would not achieve: retrofit work will aim for life-safety performance to protect occupants and to modernize infrastructure, but the building would not be certified as an emergency shelter with 24–48 hour functional recovery unless the commission elected to add that higher standard and the associated costs. The presentation closed with thanks to library board members present for the briefing and a commitment to return with design details as they stabilize.