Daggett County MBA: water treatment bond nearing closing, target set for April 16
Summary
Officials said the water treatment plant bond is "getting closer to closing," with planned reviews with CIB counsel and a target closing on April 16; the bond discussion did not address the clinic loan, which staff said they will follow up on.
Get email alerts on the Water Treatment Plant topic
No spam. Unsubscribe anytime.
Speaker 1 opened the meeting and asked for updates on the water treatment plant project. Speaker 2 said he had "spoke[n] with Eric Johnson" and that the bond is "getting closer to closing it." He said signatures will be coordinated with county staff and that there will be a review with CIB bond attorney Bill Prater before a closing planned for April 16, 2025.
Speaker 3 said they emailed Kimberly to note that Friday "wasn't the best day" for signing. Speaker 2 emphasized the current comments applied to the water treatment plant bond only and that he had not asked Eric Johnson about the clinic bond and would follow up to confirm status for both projects.
No formal motion or vote was recorded on the bond during the morning session; the board discussed logistics and timing. The body recessed at 09:27 a.m. and will reconvene at 2:00 p.m. for the clinic pre-bid meeting, at which staff said they would continue coordination on project schedules and signing requirements.