Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Sr60 Potrero topic

No spam. Unsubscribe anytime.

RCTC approves SR‑60 Potrero Boulevard contract award to Ames Construction; vote recorded 24–0

Riverside County Transportation Commission · December 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved awarding the SR‑60 Potrero Boulevard Phase 2 construction contract to Ames Construction; staff reported the contract would be approximately $53.8 million with a contingency of about $4.8 million and that construction is fully funded with a mix of local, state and federal funds including $33.5 million in TCIP money.

The Riverside County Transportation Commission approved staff’s recommendation to award the Phase 2 Potrero Boulevard interchange construction contract on State Route 60 in Beaumont to Ames Construction.

John Terascio, senior capital projects manager, outlined the project scope — Potrero Boulevard widening to six lanes, new ramp connections to SR‑60, and realignment of Western Knowles Avenue — and said design was completed in March 2025. Seven bids were received and Ames was the lowest responsive and responsible bidder; staff reported Ames’ bid was about 9.8% below the engineer’s estimate.

Staff recommended awarding the contract to Ames with a project contingency of roughly $4.8 million and a not‑to‑exceed contract amount of about $53.8 million. Terascio said construction is fully funded by a combination of local, state and federal funds, including $33.5 million in Trade Corridor Enhancement Program (TCEP) funds allocated by the California Transportation Commission.

The commission recorded the motion and the chair announced the vote: the motion passed 24–0.

Next steps: staff will finalize contract execution and schedule work to start in early 2026 with completion expected in 2028, and the City of Beaumont will reimburse the commission for project costs per the cooperative agreement.