VDOT tells Hanover supervisors $7.8 million planned for county resurfacing; SmartScale and TAP timelines set

Hanover County Board of Supervisors · January 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

VDOT Ashland residency presented resurfacing and grant updates, including a roughly $7.8 million resurfacing investment in Hanover, a strong TAP score for an Atlee Road pedestrian project, and SmartScale pre-application and full-application dates (March 2 and June 2).

Philip Frazier, VDOT resident engineer for the Ashland Residency, briefed the Hanover board on maintenance and capital programs, telling supervisors that VDOT anticipates approximately $7.8 million in resurfacing investment in Hanover County for the coming program year.

Frazier outlined three resurfacing contract types—plant-mix asphalt overlays, surface-treatment chip seals, and slurry/cape seals—explaining where each treatment is commonly used. He highlighted a Transportation Alternatives Program (TAP) application for pedestrian improvements on Atlee Road near Combs that scored seventh in the state and second in the Richmond District, and noted that scorecards will go to the Commonwealth Transportation Board and may be adopted into the Six-Year Improvement Program.

Frazier also reminded the board that the SmartScale pre-application process opens March 2 and full applications open June 2, encouraging county staff to pursue funding for local priorities. He provided an overview of planned projects that will be shared with staff and said he will return with distribution lists for specific route treatments.

Board members thanked VDOT for cooperation on local constraints and asked follow-ups on resurfacing timelines, specific project lists and pothole follow-ups; VDOT offered to coordinate and distribute the project list to county staff later in the week.