Commission approves $19,198 change order to lower Sterling Lincoln Ave pond weir by 4 inches

Goshen Redevelopment Commission · January 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved Change Order No. 5 for Sterling Lincoln Avenue (job 20190046) after staff said an emergency overflow weir was installed 4 inches too high in 2019; Niblock provided a $19,198 quote to remove/restore riprap and landscaping to protect parking-lot and roadway elevations.

Engineering staff presented Change Order No. 5 for the Sterling Lincoln Avenue reconstruction and drainage improvements (job 20190046). Staff said due diligence on the La Casa development revealed the retention-pond emergency overflow weir sits approximately 4 inches higher than intended, which reduces the pond’s emergency freeboard and could allow standing water on Lincoln Avenue during a 100-year event. Staff recommended lowering the weir by 4 inches to restore design elevations and protect the adjacent parking lot and low rim elevations on Lincoln Avenue.

Speaker 4 described the scope and costs: removing and replacing riprap and restoring landscape would be the majority of the expense; Niblock (contractor) quoted $19,198. Staff stated that the structure appears to have been installed incorrectly in 2019 and that earlier projects lacked a formal weir-check process. Commissioners asked who installed the weir and whether liability exists; staff said the installation likely predates current internal check procedures.

A motion to approve Change Order No. 5 was moved, seconded and approved. The transcript records the vote as 'that has passed 4 to 0.'

Next steps: staff will execute the change order with the contractor and schedule restoration work, and will continue to check weir heights on future projects to avoid recurrence.