Council approves up to $26,990 for design changes to GBRA water main; Fair Oaks Ranch to reimburse
Summary
The council authorized an amendment to the professional services contract with Kimley‑Horn for additional design services on the GBRA water main extension, not to exceed $26,990, with Fair Oaks Ranch agreeing to reimburse approximately $24,002.60 toward the changes.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Boerne City Council on Dec. 9 approved resolution 2025‑R91, authorizing the city manager to execute an amendment to the professional services contract with Kimley‑Horn and Associates, Inc. for additional design services on the GBRA water main extension project, for an amount not to exceed $26,990.
Andrew Wilkins presented the project details, noting the water main is a 16‑inch extension that will tie into GBRA's existing 24‑inch main and run to a future tank and pump station to provide redundancy and fire‑flow protection. The project is one of three concurrent efforts east of town along Ammon Road and is currently 100% design complete. Wilkins said planned roadway softening by Fair Oaks Ranch required additional design considerations — including casing pipe under the future roadway — and Fair Oaks Ranch has agreed to reimburse the city for the design changes and associated construction costs.
“We have to implement some design considerations into the main extension project, including casing pipe under that future roadway,” Wilkins said, and confirmed that Fair Oaks Ranch has agreed to reimburse the city for these design changes. At the meeting staff clarified the reimbursement figure as approximately $24,002.60. The resolution authorizes additional design work and consolidates electric service to one service point, which staff said would reduce construction costs overall despite the upfront design expense.
Councilmember Bunker moved approval; the motion was seconded and the council approved the resolution (vote reported as positive).
Ending: The amendment authorizes up to $26,990 for additional design services; staff said Fair Oaks Ranch will reimburse the city for a significant portion of the added design cost and the consolidated electric service should lower construction costs.