Hazel Avenue reconstruction 11% complete, village says; water main, storm sewer and directional drilling work underway

Village of Deerfield Board of Trustees · April 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Village public works reported that Hazel Avenue reconstruction is approximately 11% complete, with about $5 million in federal/county funds offsetting a roughly $10 million project; contractors are installing a 42-inch storm sewer, new water main and preparing directional drills under the creek and railroad.

Village public works staff gave trustees a detailed update April 7 on the Hazel Avenue reconstruction project, saying the federally supported infrastructure overhaul is underway and tracking toward a fall completion for major construction work.

Public works staff said design work began in 2020 and construction began in early March 2025. The project, which staff described as carrying an overall construction price in the vicinity of $10,000,000 plus engineering, includes relocation of utilities, a 42-inch storm sewer, new water main installation,…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans