Board approves EMS billing contract, leaf‑disposal change order and stormwater engineering agreement
Summary
Trustees unanimously authorized a new EMS billing-services agreement with EMSMC (service fee reduced to 4.5%), approved a $9,000 change order for additional leaf disposal, and authorized up to $38,000 for design engineering on the Scottsdale headwall replacement.
Get email alerts on the Contracts And Procurement topic
No spam. Unsubscribe anytime.
At its meeting, the La Grange Park board approved three contract actions and took a procedural vote to enter executive session.
EMSMC billing agreement: The board approved a resolution authorizing execution of a billing‑services agreement and business associate addendum (HIPAA) with EMS Management & Consultants, Inc. (EMSMC), which acquired the village's prior provider, Andres Medical. Staff reported the service fee will drop from 4.75% to 4.5% and the agreement runs through Jan. 31, 2027, with automatic annual renewals. Trustees asked staff to confirm that billing procedures and the handling of resident charges would not change; staff said terms and collection practices remain the same.
Leaf‑disposal change order: Public works presented Change Order No. 1 to the Landscape Material and Firewood Sales Inc. leaf‑hauling contract to account for heavier, snow‑saturated loads that reduced truck capacity; the board approved a not‑to‑exceed $9,000 increase that raises the contract from $36,000 to $45,000.
Scottsdale headwall engineering agreement: Trustees authorized a professional‑services agreement with Edward Hancock Engineering Company for design services related to the Scottsdale storm‑sewer headwall replacement. Staff said additional permitting raised the expected design cost above the $14,000 budgeted amount; the board approved spending up to $38,000 from sewer funds for the design.
Executive session: The board voted unanimously to adjourn into executive session to discuss personnel matters under 5 ILCS 120/2(c)(1) and indicated it would not reconvene to open session until the next regular meeting on Feb. 10, 2026.
All contract and change‑order measures were approved by unanimous roll call.