Commissioners sign engineering contract and advance Cattail Bay, Bridal Avenue road projects

Emmons County Board of Commissioners · February 4, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Road staff reported awarded flex and SRF funding for multiple county road projects; commissioners approved a preliminary engineering agreement with Wolf Engineering for the Cattail Bay cement-stabilization project and discussed wetland mitigation and culvert costs.

Road staff updated commissioners on a suite of projects and funding streams and the board approved a preliminary construction-engineering agreement to move a major Cattail Bay project forward.

Speaker 8 said the county received a flex-fund award for a Bridal (17th Avenue) project; plans have been submitted to the state DOT and staff noted a US Fish and Wildlife wetland mitigation review that could take 6–9 months and estimated mitigation costs of about $10,000. He also outlined an awarded cement-stabilization grant for Cattail Bay (approximate award described as roughly $300,000 for 2 miles) and explained the trade-offs of addressing an aging box culvert immediately (possible additional cost in the hundreds of thousands) versus deferring that expensive work until a later funding round.

After discussion on base materials, hauling clay vs. using county crews, bidder options and timing windows (mid-June through August preferable for minimizing conflicts with harvest), the board approved a preliminary construction-engineering services agreement with Wolf Engineering to support SRF application and project design. Speaker 2 moved to approve the contract and the board carried the motion.

Next steps: the county will continue design with Wolf Engineering, finalize SRF application components, study culvert options and cost shares, and evaluate clay-borrow and contractor pricing vs. county performance for the base material work.