Bluff council approves $12,656 sidewalk and grading bid for new playground, covers small budget gap

Bluff Town Council · February 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $12,656 bid from Pueblo Tierra Construction for a playground sidewalk and grading; playground costs total about $180,191 including prior commitments and grant match, leaving an estimated $2,191 shortfall the town will cover from parks budget contingency.

Bluff — The council approved a contract to complete a sidewalk perimeter and grading for the town’s planned playground.

Parks staff Malia reported the town received one responsive bid from Pueblo Tierra Construction for $12,656 to install a sidewalk around the playground, grading and retaining-wall work, and related site work. The playground contract and related commitments total roughly $180,191 versus a $165,000 grant and a $13,000 cash match; staff said the town’s remaining net exposure, if the council approved the bid, would be about $2,191.

Malia said the bid covers the perimeter sidewalk, connections to the pavilion and kitchen, grading and the sport-court fence; she proposed completing the playground perimeter and installation first and deferring work on the sport court to use in-kind grading later.

When asked about budget impact, finance/staff said parks and recreation has sufficient contingency in the approved annual budget, and the town would not exceed the approved budget by accepting the bid.

Council called for a vote to approve the sidewalk and grading vendor; the motion passed with one abstention (the transcript does not record the abstaining member’s name). Staff will proceed with contracting and scheduling work to complete the playground perimeter.

What’s next: Staff to finalize contract with Pueblo Tierra Construction and schedule installation; sport-court installation may follow as a later phase.