Officials report New Hanover High renovation on schedule, phase 2B planned for summer; community engagement event set Feb. 27
Summary
District facilities staff reported phase 2A wall replacements are on schedule and slightly under budget; phase 2B work and the security vestibule will continue through summer, and a facilities assessment/master plan is due in April with a public engagement event scheduled Feb. 27.
District facilities staff updated the New Hanover County Schools Board Feb. 4 on progress at New Hanover High School and plans for master planning and community engagement.
The presentation said work in “Phase 2A” — removal and replacement of the eastern and western flanking walls — is on schedule and slightly under budget after a change order approved in December. District staff described the upcoming Phase 2B…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat