SFPUC quarterly capital report: BDFP reaches major construction milestones as SSIP remains a $4.7 billion program
Summary
SFPUC staff reported construction progress across wastewater projects, including the Southeast Plant biosolids digester (BDFP) now over 80% complete in construction and forecast variances tied to a $164.5 million biogas component and a $44 million Lower Alemany stormwater project.
Bessie Tam, Wastewater Enterprise Capital Programs Director, told the San Francisco Public Utilities Commission that the department’s Q2 fiscal-year 2024–25 capital report shows substantial progress across the Sewer System Improvement Program (SSIP) and the Southeast Plant biosolids digester facility (BDFP).
“Construction as of this quarter is over 80% complete,” Tam said, summarizing the BDFP construction status and noting the overall program is more than 60% complete. She said the SSIP remains a $4.7 billion approved program and identified two primary…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat