Hetch Hetchy capital program reports ongoing shutdown work, cost increases on Moccasin projects
Summary
SFPUCreported progress on 22 Hetch Hetchy projects through Dec. 31, including a 100‑day system shutdown that completed major tunnel lining repairs, and forecasted cost increases (Moccasin powerhouse +$15M; Moccasin Dam +$23M) on several projects.
Katie Miller, Director of Water Capital Programs, summarized the Hetch Hetchy Capital Improvement Program through Dec. 31, 2024. She said staff added five new projects this fiscal year for a total of 22 tracked projects across water, power and joint water‑and‑power categories. Miller reported $65,000,000 spent in the first and second quarters and that there are currently 10 construction contracts underway.
Miller highlighted work completed during a recent 100‑day winter shutdown (Dec. 5 to March 10):…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat