Katy Development Authority authorized to use up to $9.71M in Metro funds for Katy Hockley widening

City of Katy City Council · June 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City of Katy authorized the Katy Development Authority to use up to $9,711,472 in Metro funds for the Katy Hockley Road widening (Morton to Clay); staff said utility relocation begins after July 4 and full completion is projected in October 2026.

KATY, Texas — The Katy City Council on June 23 approved a resolution authorizing the Katy Development Authority (KDA) to use Metro funds for the Katy Hockley Road widening project between Morton Road and Clay Road, authorizing up to $9,711,472, which includes a 5% contingency on the bid award of $9,249,021.

Council and staff discussed the project schedule and traffic infrastructure. A council member asked whether a traffic signal at Katy Hockley and Morton was included; a staff/contract representative said the traffic signal is already under construction and expected to be operational by July. Staff described the contract as a 420-day work plan, with private utility relocation to begin after the July 4 holiday and contractor mobilization likely in September; projected completion was described as October 2026.

Why it matters: The authorization commits Metro and KDA funding toward a major arterial-widening project that will affect traffic patterns, utility placements and neighborhood access across Katy; the dollar amount and contingency add budgetary significance.

Funding and procurement details: Bids were received May 29; KDA awarded the project on June 16, 2025, at $9,249,021. The council’s authorization allows the KDA to use Metro funds up to the $9,711,472 cap to cover the bid and contingency.

Next steps: Staff indicated utility coordination is a near-term dependency; the contractor will coordinate private utility relocations and then proceed with mainline work per the 420-day contract schedule. The city and KDA will monitor construction timelines and traffic signal activation.

Reporting note: Figures and schedule notes are taken from the June 23 meeting transcript.