Bulloch County commissioners approve EMS equipment, multiple road contracts and task orders; FEMA reimbursements update provided
Summary
At its December meeting, Bulloch County commissioners received an EMA update on FEMA obligations and approved a string of purchases and contracts including ZOLL cardiac monitors, right-of-way work for Country Club Road, change orders on a fire station project, and road-design and construction contracts; Cypress Lake Road remains on a 2026–27 timeline.
Get email alerts on the Meeting Roundup topic
No spam. Unsubscribe anytime.
Bulloch County commissioners heard an emergency management update on disaster recovery funds and approved several procurement and construction actions during a regular meeting.
Corey Kemp, the county’s director of emergency management, told the board FEMA has obligated three previously pending CRC projects and that most non-highlighted projects are closed or paid. Kemp said remaining work includes ditching and road repairs, and that he will seek routine 12-month extensions for project periods of performance that otherwise expire in March.
On purchases and contracts, the board:
- Approved a sole-source purchase of three ZOLL Zenix cardiac monitors from ZOLL Medical Corporation for $155,206.08 to replace older monitors; the motion carried unanimously after staff noted the county budgeted $140,000.
- Approved a $20,250 task order (FY26ROWE08) with on-call consultant JMT for right-of-way acquisition affecting four parcels for the Country Club Road culvert replacement project; the task order will be funded with T-SPLOST funds and passed unanimously.
- Approved a $20,828.35 change order with Sims Paving and Construction LLC to address field conditions on the register fire station project (move generator and LP tank, install AC units and sidewalk work); the board approved the change order unanimously.
- Authorized a $42,500 contract with Peyton Dawson Engineers to design approximately 1,800 linear feet of Anderson Cemetery Road through Cornerstone Pointe subdivision; the motion passed 5–1.
- Awarded a $214,913.05 construction contract to Sims Paving and Construction LLC for a right-turn deceleration lane from State Route 67 onto Anderson Cemetery Road after soliciting quotes; commissioners approved the low quote on a 5–1 vote.
County engineer Ron Nelson provided a Cypress Lake Road update: geotechnical borings were completed, procurement for a contractor is expected in April 2026, construction would take about 15 months and the roadway could reopen in August 2027. Nelson said a full bridge replacement was chosen because the existing structure was rated for eight tons and was already impassable for school buses.
Staff reports covered internal insurance renewal work, a January discussion about septic waste handling, continued EMS hiring for a new Stilson station and an interim lowering of some hiring standards to allow new hires time to become certified. The board closed with community remarks, condolences for a Stilson house fire, holiday wishes and a motion into executive session to discuss real estate under OCGA fifty-fourteen-three B1B; the chairman said he did not anticipate action after the session.