Delaware County wastewater board approves $198,705.35 in January claims, releases rehab retainage

Delaware County Wastewater District · February 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Delaware County Wastewater District approved $198,705.35 in claims for mid-December through January, released retainage for a completed rehab project, and reviewed collections and maintenance issues at its Feb. 4 meeting.

The Delaware County Wastewater District board approved claims totaling $198,705.35 for the period 12/03/2025 through 01/30/2026 and reviewed account balances and year-end items at its Feb. 4 meeting.

Speaker 5 reported the claims total and the district’s account balances, saying the cash operating balance was approximately $420,000 and the improvement fund balance was $2,499,492.92. Speaker 5 moved to approve the January claims; the motion was seconded and carried on roll call.

The board voted to release retainage for a completed rehabilitation project and discussed when the warranty period began. A board member asked whether the warranty period started at substantial completion; staff confirmed the warranty start at substantial completion and the board proceeded with release of the retainage.

Staff also updated the board on collections and maintenance. Collections rose to $2,058.44 from $278.05 a month earlier after field letters were delivered; a surplus plow sold at auction for $2,025. Staff noted a variable-frequency-drive fault on station 1 during cold weather that was addressed by the contractor’s heater installation.

The board took the actions as part of routine fiscal oversight; no further funding allocations or budget amendments were proposed at the meeting.