Richland County completes administration building renovations, opens new courtroom
Summary
Richland County completed renovations to its County Administration Building in 2025, adding a 2,700-square-foot courtroom, relocating the Clerk of Courts, modernizing public spaces and critical systems, and updating accessibility and staff amenities, county officials said.
Get email alerts on the Facilities Renovation topic
No spam. Unsubscribe anytime.
An unidentified presenter, Presenter, said Richland County completed extensive renovations to the County Administration Building in 2025 that included a new courtroom and upgraded public and staff spaces.
The presenter said the Clerk of Courts relocated in 2024 to a new office on Level L2, which "provided staff with a more functional space to efficiently manage a docket of approximately 6,000 cases each year." That move, officials said, created room for construction of a "brand new state of the art courtroom for the Common Pleas General Division."
Courtroom Number 4, the presenter said, "opened to the public in September" and "spans 2,700 square feet" with "modern finishes, new windows, custom furnishings, and enhanced security." The presenter added that the project also "includes a fully modernized jury room equipped with the technology and comfort necessary for effective deliberation."
Officials said the new courtroom increases the number of courtrooms available to the public by 33%, a change the presenter described as helping "to eliminate delays in the court's docket caused by limited space for trials and hearings."
Renovations extended beyond courtrooms. The presenter said the county modernized 4,600 square feet of common areas that dated to the building's original 1968 construction, installing brighter finishes, new ceilings with energy-efficient lighting and upgraded seating. The Land Bank offices were reconfigured from outdated space "that once included an old jail" into customized workspaces and a state-of-the-art boardroom, with an elevated public seating area added to improve the visitor experience.
All 10 of the building's restrooms "were fully updated with new fixtures, flooring, wall tile, and ADA compliant accessibility," the presenter said. The county also added a new break room and used wellness funds to upgrade an exercise room for employees and community control staff with quality fitness equipment to support staff well-being.
The project included a new training room for the Community Control Department intended to expand staff development opportunities supporting that department's rehabilitation mission. Critical infrastructure and security systems were modernized as well: the presenter cited upgrades to fire protection, electrical and HVAC systems, all equipped "with the latest digital controls."
The county said the combined improvements will allow the County Administration Building "to operate safely, efficiently, and sustainably for decades to come," and that the modernizations will improve government efficiency and the experience of residents doing business in Richland County. The announcement did not specify costs, funding breakdowns or a timeline for any remaining work.