Summary

Superintendent presented a roughly $40,000,000 capital project to be decided by a community vote on Dec. 9, saying state building aid, reserves and planning would cover costs and that the district expects no tax increase; major items include a middle‑school roof, energy upgrades and a synthetic turf field.

Superintendent (Speaker 3) told the Gloversville City School District board the district will ask voters on Tuesday, Dec. 9, to approve a capital project with an estimated cost of about $40,000,000.

The project, the superintendent said, is intended to improve safety, energy efficiency and functionality across district facilities while avoiding any increase to local property taxes. "We think to the taxpayers that it will have a 0 impact on our tax," the superintendent said during the presentation.

The proposal highlights included a full middle‑school roof replacement (the roof is off warranty and leaks have been reported), replacement of outdated heating systems with energy‑efficient boilers, and a secure vestibule for the district office. At Boulevard, the plan calls for a new main entrance by the bus zone to improve traffic flow and reduce a winter slip hazard in the current atrium design.

Athletic upgrades were a focal point: the plan would install a synthetic turf surface at Husky Stadium to support football, baseball and other regional events, and would add parking and a safer parent drop‑off at Park Terrace. District officials said turf would address chronic drainage and substrate problems on the existing field and could expand use for practices, community events and graduations.

Superintendent presentation materials say the project would be funded through a combination of New York state building aid, capital reserves and strategic financial planning. No formal vote on the project occurred at the meeting; the community vote is scheduled for Dec. 9, with polling hours listed in the presentation.

If approved, the district said it would also pursue smaller improvements across multiple buildings—security, infrastructure, and long‑term energy savings—that are intended to protect district facilities and expand community engagement opportunities.

The board will publish project materials on the district website and social channels and hold outreach events so taxpayers can review details before the Dec. 9 vote.