Select Board authorizes town staff to proceed with reduced‑scope Furbish Road FLAP project
Summary
Board authorized the town manager and town engineer to sign MDOT agreements and design contracts to pursue a reduced‑scope Federal Lands Access Program (FLAP) sidewalk project on Furbish Road, an 80/20 federal‑to‑town reimbursement grant that must be implemented this year or funds must be returned.
Get email alerts on the Transportation Grants topic
No spam. Unsubscribe anytime.
The Select Board on Jan. 20 authorized town staff to move forward with a reduced‑scope Federal Lands Access Program (FLAP) project for Furbish Road and to sign updated Maine DOT agreements and design contracts.
Staff summarized the grant’s history: the town initially received FLAP funding for sidewalks linking Route 1 to a view platform, but rising costs and project sequencing led staff to complete Harbor Road first. Remaining FLAP funds are time‑limited and must be used this year or returned. Staff proposed scaling back the Furbish work to a paved sidewalk from the Furbish Road culvert to Ocean Avenue and reconstruction of the viewing platform to meet ADA standards.
The grant structure is an 80/20 reimbursement (federal funds administered by Maine DOT cover about 80% of eligible costs; the town provides 20%). Staff said the town’s local share is in a dedicated reserve account and no new tax dollars are required.
Board members asked about design completion (staff said roughly 60–70% complete), drainage, whether the sidewalk would be raised (answer: a 5‑foot grass esplanade and then a paved sidewalk, not a raised sidewalk), crosswalk placement and temporary plastic delineators over a narrow culvert for pedestrian safety. The board moved to authorize the town manager and town engineer to pursue the project and to sign the MDOT agreement and related documents; the motion passed unanimously.
A staff member emphasized urgency: "If we don't get it done this year, it's then we have to give the money back." The board authorized staff to continue design, permitting and bidding under the updated agreement.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.