Commission approves $78,952 change order after expanded soil remediation at Memorial Park site

Hammond Redevelopment Commission · February 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved a $78,952 change order to cover increased disposal and remediation costs at the Memorial Park subdivision after further delineation found greater volumes of contaminated soil than initially estimated; commissioners emphasized safety for children and future residents.

The Hammond Redevelopment Commission approved a $78,952 change order Jan. 20 to cover additional soil excavation and disposal costs related to the Memorial Park subdivision remediation.

City project staff and the engineer told commissioners this is the third change order for the project. Initial planning assumed removal of about 500 tons of contaminated material; further delineation identified both a pocket that exceeded the worker exposure limit and a larger area that needed remediation to residential standards. During the presentation staff cited a residential remediation volume of 944.81 tons and described the total removed as substantially higher than originally anticipated. The additional disposal and remediation expenses resulted in the requested $78,952 change order.

Staff emphasized that remediation focused on the identified contamination zones and that the work was necessary to protect future residents, particularly small children and seniors. Commissioner Shelton moved to approve the change order and Commissioner Talmadge seconded; the commission approved the change order 5-0.

The city engineer said the remedial approach limited exposure and targeted the specific affected areas, and staff said they aimed to complete remediation before further development.

Provenance: explanation and figures provided by the city engineer during the Memorial Park change-order agenda item.