Gravette construction update: footings and slab scheduled; board approves six-classroom addition
Summary
Construction superintendent reported footings near completion, slab pour expected by month-end and structural steel arrival the week of Feb. 23; the board approved a $84,173.75 contract for a six-classroom Gravette High School addition.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Construction supervisor Austin Lee told the board the site building pad work began before Christmas, that footings were about 75% complete and that slab preparation would begin the following week with a slab pour expected by the end of the month. Lee said plumbing rough-in and water meter installation had passed inspection and that structural steel delivery was scheduled for the week of Feb. 23.
During the meeting the board approved a proposal to furnish a six-classroom addition to Gravette High School for $84,173.75. District staff said ordering now would allow the vendor to have the units ready for an Aug. 1 move-in. The vendor name in the transcript appears as "Losers," and staff noted they had sourced a vendor familiar with the original high-school work to keep finishes consistent.
"We started footings a couple weeks ago... anticipate the slab will be poured by the end of the month. Structural steel is scheduled to be delivered the week of 02/23," Lee said.
Board members asked about drainage tiles and contingencies; staff reported no engineering issues and that drainage/storm-drain installations were at the appropriate depth. The board approved the six-classroom contract by voice vote and directed facilities staff to proceed with procurement and scheduling.