Port St. Joe approves sewer, stormwater and demolition items; authorizes emergency repair and task orders
Summary
The commission accepted updates from Anchor CEI on sewer rehab (Phase 2 nearly complete; Phase 3 ~15% done), approved an emergency clarifier repair for $58,438, authorized a task order for the MLK project (approx. $1.7M), approved voluntary demolition permits and event fee waivers, and advanced water-tank replacement planning.
City staff and consultants updated the commission on multiple infrastructure projects and the board approved several routine and emergency items.
Sewer and utilities: Elizabeth Moore of Anchor CEI said Phase 2 pump and station work is largely complete and Phase 3 gravity-sewer rehabilitation is about 15% complete, with crews starting work between Long and Woodward and camera inspections underway. The contractor completed the most difficult segment near Highway 98 early to avoid conflict with a DOT paving project; staff estimated DOT resurfacing will…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat