Facilities committee approves release of RFP to demolish former nursing home on East Main Street
Summary
The Champaign County Facilities Committee voted to release an RFP to demolish the vacant nursing home at 1701 E. Main Street in Urbana and will accept bids; staff estimated a project cost of about $1.4 million including modifications, with earlier demolition-only estimates nearer $900,000–$1,000,000.
Get email alerts on the Nursing Home Demolition topic
No spam. Unsubscribe anytime.
Champaign County’s Facilities Committee on Tuesday approved the release of a formal request for proposals to demolish the vacant nursing home at 1701 E. Main Street in Urbana.
The committee voted by voice to release the ITB for selective demolition after staff and consultants from Bailey Edward reviewed plans and specifications. Carla Smalley of Bailey Edward said the full plans are posted online and that the pre-bid meeting will be open to interested bidders and is intended to let potential contractors visit the property and ask questions; answers will be distributed via an addendum.
Smaller details of the structure’s condition were discussed: a consultant said the building’s interior is unsalvageable owing to mold, and county staff identified five exterior decorative pieces the county would like to preserve. Contractors bidding on the work will be told to assume the presence of lead-based paint and to stop and notify staff if they encounter asbestos or other hazardous materials during demolition.
Staff described the project estimate as roughly $1.4 million when including modifications to close a connection to an adjacent building; earlier estimates for straight demolition (without that connection work) had been in the $900,000–$1,000,000 range. The bid opening date in the packet is February 24 (time listed as 4:00 p.m. as a placeholder). Highway staff will share some costs because the county expects highway to build a cold-storage facility on the cleared site after demolition.
The motion to release the RFP was moved and seconded (motion recorded as moved by Member Aris and seconded by Member Wiggs) and passed by voice vote; the transcript does not record a roll-call tally. Staff said the full bid documents total about 200+ pages and are available on the county’s facilities page for bidders to review.
The committee discussion also covered alternate removal scopes (garages and the boiler building) and practical bidding logistics. Committee members and staff emphasized safety and that the site will be fenced during demolition.
Next steps: staff will publish the plans and collect bids on the public date listed in the bid documents; award and contract recommendations will return to the committee per the usual procurement process.