Board approves amended LTFM plan after pool/IAQ bids exceed estimate; district will cash-flow extra cost until levy adjustment arrives
Summary
The board approved an amended Long-Term Facilities Maintenance (LTFM) plan after bids for pool and indoor-air-quality work exceeded initial estimates; staff said an additional $1,000,078.06 will be recovered through a future levy adjustment, requiring short-term cash flow borrowing.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Big Lake Public School District board approved an amended Long-Term Facilities Maintenance (LTFM) plan to reflect higher-than-anticipated costs for a pool and indoor-air-quality (IAQ) project.
District staff and project leads said initial planning estimated the work at about $1.3 million but that detailed inspection and contractor bids revealed additional necessary repairs and replacements — including piping, lighting and anchors in the chlorine environment, and replacement of the pool and locker-room air handlers — that raised the cost. Staff highlighted an additional cost figure of $1,000,078.06 and explained how the state’s levy-adjustment timing means the district will receive corresponding revenue in later years. In the interim the district will need to cash-flow the project from fund balance and then repay that balance when levy adjustments are realized.
TJ, who presented details about the scope changes and the replacement of components to lengthen service life, said the project includes removing corroded metal and installing longer-lasting materials such as fabric ducting and new anchors.
Board members asked whether the additional LTFM draw would delay other planned projects. Staff said the extra cost is accommodated by additional levy authority and will not force postponement of other immediate projects; they also noted many bonded-project payments will decline in coming years, freeing capacity for future work.
The board approved the amended plan in its routine business section. Staff said the timing for levy adjustments is driven by final UFARS data and state processes, which can create a multi-year lag between expense and levy reimbursement and therefore a temporary LTFM fund deficit that is permitted under the funding rules.
The board did not vote on specific contractor awards at the meeting; the agenda item adjusted the LTFM plan and documented the district’s approach to cash-flowing the additional cost until state levy adjustments are applied.